The County-linked dashboard exposes current status for 70 projects. Tax Watch exactly reconciled 45 of those ARP codes to the County’s newest posted Treasury project report, a historical accounting snapshot through June 30, 2023.
ARP-1000 · Low alert · 83.3% dashboard progress
$664,104.98 cumulative expenditures · $722,454.04 obligations · $3,500,000.00 adopted budget as of 2023-06-30
Latest Update ✓Install Alamo Equipment - 2/28/23 ✓Install Radios - 4/30/23 ✓Project Close - 5/31/23
Public Health · Mental Health · Project 1.1.1 · Treasury evidence p. 23
ARP-1010 · On track · progress not reported
$1,300,850.28 cumulative expenditures · $4,626,449.04 obligations · $5,429,604.00 adopted budget as of 2023-06-30
Latest Update. Engineering services for this task encompass both design and construction management activities. With the design phase complete, the consultant continues to provide construction-phase services, including coordination with the construction management team and Resident Project Representative (RPR) to verify that the contractor’s work is performed in accordance with the approved plans and specifications. These services will continue throughout construction and include all required project closeout activities through final completion and acceptance of the project.
Critical Infrastructure & Support Services · Water & Wastewater Improvements · Project 2.1.1 · Treasury evidence p. 19
ARP-1011 · On track · progress not reported
$0.00 cumulative expenditures · $0.00 obligations · $28,570,396.00 adopted budget as of 2023-06-30
Latest Update. The majority of the Lower Valley/Far East Area projects are substantially complete and are progressing through final closeout activities. Panorama Village is anticipated to reach substantial completion by September 30, 2026. The Northwest Area Project is also substantially complete, with final completion anticipated by October 20, 2026.
Critical Infrastructure & Support Services · Water & Wastewater Improvements · Project 2.1.2 · Treasury evidence p. 26
ARP-1020 · Completed · progress not reported
$34,752,896.00 cumulative expenditures · $34,752,896.00 obligations · $34,752,896.00 adopted budget as of 2023-06-30
Latest Update
Public Health · General Public Health · Project 1.2.1 · Treasury evidence p. 30
ARP-1030 · Completed · progress not reported
$1,643,329.00 cumulative expenditures · $1,643,329.00 obligations · $3,000,000.00 adopted budget as of 2023-06-30
Latest Update Project has been completed and remaining fund balance will be swept into Reserves.
Public Health · General Public Health · Project 1.2.2 · Treasury evidence p. 28
ARP-1040 · Completed · progress not reported
$2,258,506.29 cumulative expenditures · $2,258,506.29 obligations · $2,258,506.29 adopted budget as of 2023-06-30
Latest Update This project is complete.
Public Health · COVID-19 Testing & Vaccination · Project 1.3.1 · Treasury evidence p. 29
ARP-1050 · Completed · progress not reported
$1,851,604.82 cumulative expenditures · $1,855,075.98 obligations · $3,977,761.02 adopted budget as of 2023-06-30
Latest Update
Administrative Operations · Revenue Replacement (Operating & Personnel) · Project 4.1.1 · Treasury evidence p. 21
ARP-1060 · Completed · progress not reported
This project is complete.
Public Health · Safe Public Facilities & Workplaces · Project 1.4.1 · no row in the June 2023 report
ARP-1070 · Completed · progress not reported
$7,616.09 cumulative expenditures · $7,616.09 obligations · $1,625,000.00 adopted budget as of 2023-06-30
This project is complete.
Public Health · COVID-19 Testing & Vaccination · Project 1.3.2 · Treasury evidence p. 8
ARP-1080 · Completed · progress not reported
Latest Update: Project is complete.
Public Health · COVID-19 Testing & Vaccination · Project 1.3.3 · no row in the June 2023 report
ARP-1081 · Completed · progress not reported
$100,102.23 cumulative expenditures · $100,102.23 obligations · $100,102.23 adopted budget as of 2023-06-30
Latest Update This project is complete.
Public Health · COVID-19 Testing & Vaccination · Project 1.3.4 · Treasury evidence p. 27
ARP-1090 · On track · progress not reported
$328,665.00 cumulative expenditures · $328,665.00 obligations · $975,500.00 adopted budget as of 2023-06-30
Latest Update The Office of Strategic Capital Development continues to monitor use of this fund.
Public Health · General Public Health · Project 1.2.3 · Treasury evidence p. 30
ARP-1091 · Completed · 100% dashboard progress
$39,500.00 cumulative expenditures · $39,500.00 obligations · $39,500.00 adopted budget as of 2023-06-30
Latest Update - Policy Complete
Public Health · Safe Public Facilities & Workplaces · Project 1.4.2 · Treasury evidence p. 22 p. 23
ARP-1092 · Completed · progress not reported
Latest Update
Public Health · General Public Health · Project 1.2.4 · no row in the June 2023 report
ARP-1093 · Completed · progress not reported
Project is complete with a final presentation to the Commissioner's Court planned for March 2026.
Public Health · Mental Health · Project 1.1.2 · no row in the June 2023 report
ARP-1094 · On track · progress not reported
Latest Update: Project study is ongoing with an expected completion date of May 2026.
Public Health · General Public Health · Project 1.2.5 · no row in the June 2023 report
ARP-1100 · On track · progress not reported
$65,371.32 cumulative expenditures · $67,351.32 obligations · $421,605.00 adopted budget as of 2023-06-30
Latest Update This fund continues to be monitored by the administrative team.
Public Health · Safe Public Facilities & Workplaces · Project 1.4.3 · Treasury evidence p. 31
ARP-1101 · Completed · progress not reported
$259,515.62 cumulative expenditures · $262,649.77 obligations · $578,395.00 adopted budget as of 2023-06-30
Latest Update: Project is complete.
Public Health · Safe Public Facilities & Workplaces · Project 1.4.4 · Treasury evidence p. 32
ARP-1110 · Completed · progress not reported
Latest Update: Project is complete.
Public Health · Safe Public Facilities & Workplaces · Project 1.4.5 · no row in the June 2023 report
ARP-1130 · Completed · progress not reported
$740,564.90 cumulative expenditures · $740,564.90 obligations · $780,000.00 adopted budget as of 2023-06-30
This Project is completed
Administrative Operations · Revenue Replacement (Operating & Personnel) · Project 4.1.2 · Treasury evidence p. 22
ARP-1140 · Completed · progress not reported
$500,000.00 cumulative expenditures · $500,000.00 obligations · $4,178,750.00 adopted budget as of 2023-06-30
Latest Update
Economic Recovery Efforts · FASTER 1.0 (Loan Forgiveness) · Project 3.1.1 · Treasury evidence p. 2 p. 3
ARP-1150 · On track · progress not reported
Latest Update Project with Spectrum is being reviewed for final walkout. Completion is currently being verified. AT&T is currently 80% completed and completion is expected by Fall 2026.
Critical Infrastructure & Support Services · Broadband Infrastructure · Project 2.2.1 · no row in the June 2023 report
ARP-1160 · On track · progress not reported
Latest Update Coordination with the Regional Mobility Authority to develop the commercial traffic study and project is on track.
Economic Recovery Efforts · FASTER 2.0 (New Program Development) · Project 3.2.1 · no row in the June 2023 report
ARP-1161 · On track · progress not reported
Latest Update The Economic Development Department has finalized agreements with the Hispanic Chamber of Commerce and Project Vida to provide small business technical and financial support, along with a comprehensive supplier development matchmaking effort. These initiatives are underway and expected to close out in the fall of 2026.
Economic Recovery Efforts · FASTER 2.0 (New Program Development) · Project 3.2.2 · no row in the June 2023 report
ARP-1162 · On track · progress not reported
Latest Update The Economic Development Department has finalized agreements with EFO Media, LJA Inc, and Destination El Paso to launch a Countywide Tourism program that includes the following tasks; Narrative of Historic Assets and Promotional Segments Museum Curation and Exhibit Design Digital Content Website and Online Presence Marketing and Awareness Promotional Resources Enhancing Tourism Attraction Efforts with AI-Driven Reports Heritage Tourism Collaborations Enhancement of the Old County Jail Ambassador Program Old El Paso County Jail Tourism Program Branding and Identity Tours and Activities These initiatives are underway and expected to close out in the fall of 2026.
Economic Recovery Efforts · FASTER 2.0 (New Program Development) · Project 3.2.3 · no row in the June 2023 report
ARP-1170 · On track · progress not reported
Latest Update Project is set for completion by the end of July 2025.
Economic Recovery Efforts · FASTER 2.0 (New Program Development) · Project 3.2.4 · no row in the June 2023 report
ARP-1171 · On track · progress not reported
Latest Update Project is set for completion by the end of July 2025.
Economic Recovery Efforts · FASTER 2.0 (New Program Development) · Project 3.2.5 · no row in the June 2023 report
ARP-1200 · On track · progress not reported
$1,710.86 cumulative expenditures · $1,710.86 obligations · $25,000.00 adopted budget as of 2023-06-30
These plans are largely on track to be completed before the end of the year. Good progress has been made and all 95 re-entry beds are filled. The Sobering Center is in progress and is just awaiting an MOU signature between EHN and their partners (this will provide 5 existing beds). Construction is due to begin in the near future to remodel the Crisis Center and provide up to 13 Sobering Center beds.
Administrative Operations · Professional Services & Technology · Project 4.2.1 · Treasury evidence p. 31
ARP-1210 · Completed · progress not reported
$116,610.00 cumulative expenditures · $181,194.00 obligations · $250,000.00 adopted budget as of 2023-06-30
Latest Update
Critical Infrastructure & Support Services · Community Assistance & Support Services · Project 2.3.1 · Treasury evidence p. 9
ARP-1220 · Completed · 100% dashboard progress
$86,399.97 cumulative expenditures · $145,090.76 obligations · $1,800,000.00 adopted budget as of 2023-06-30
Project construction completed and final state jail inspection schedule February 2025.
Public Health · Safe Public Facilities & Workplaces · Project 1.4.6 · Treasury evidence p. 14
ARP-1230 · Completed · progress not reported
$97,622.64 cumulative expenditures · $97,622.64 obligations · $861,591.00 adopted budget as of 2023-06-30
Latest Update
Critical Infrastructure & Support Services · Community Assistance & Support Services · Project 2.3.2 · Treasury evidence p. 9 p. 10
ARP-1240 · Completed · progress not reported
$90,145.71 cumulative expenditures · $90,145.71 obligations · $1,088,202.00 adopted budget as of 2023-06-30
Latest Update
Critical Infrastructure & Support Services · Community Assistance & Support Services · Project 2.3.3 · Treasury evidence p. 5
ARP-1250 · Completed · progress not reported
$185,976.38 cumulative expenditures · $185,976.38 obligations · $600,000.00 adopted budget as of 2023-06-30
Latest Update
Administrative Operations · Revenue Replacement (Operating & Personnel) · Project 4.1.3 · Treasury evidence p. 20
ARP-1260 · Low alert · 97% dashboard progress
$220,111.24 cumulative expenditures · $525,489.72 obligations · $600,000.00 adopted budget as of 2023-06-30
Latest Update
Public Health · Safe Public Facilities & Workplaces · Project 1.4.7 · Treasury evidence p. 24
ARP-1270 · Completed · 100% dashboard progress
$0.00 cumulative expenditures · $393,661.10 obligations · $448,500.00 adopted budget as of 2023-06-30
Latest Update ✓Project Complete - 9/1/22 ✓Implementation of DDOS Mitigation Service - 8/31/22
Administrative Operations · Professional Services & Technology · Project 4.2.2 · Treasury evidence p. 27 p. 28
ARP-1280 · Completed · 100% dashboard progress
$3,355,204.58 cumulative expenditures · $3,557,084.64 obligations · $3,557,084.64 adopted budget as of 2023-06-30
Latest Update ✓Jail Annex - 7/31/25 ✓DDF - 9/30/25 ✓Project Complete - 9/30/25
Public Health · Safe Public Facilities & Workplaces · Project 1.4.8 · Treasury evidence p. 10
ARP-1290 · Completed · 100% dashboard progress
$67,421.25 cumulative expenditures · $93,501.25 obligations · $420,000.00 adopted budget as of 2023-06-30
08/28/2025 The iSpeak915 project has been completed and is now live. The Limited English Proficiency (LEP) plan has been finalized, and training has been conducted with selected departments. Additional departments will be added in the next phase. Promotion of the service has begun through newsletters, social media, and community presentations. Updates will be provided to Commissioners Court as needed to report on the launch and ongoing progress. Latest Update ✓Deploy County Training - 3/30/23 ✓Conduct Outreach - 4/30/23 ✓Complete Project - 5/30/23
Public Health · Safe Public Facilities & Workplaces · Project 1.4.9 · Treasury evidence p. 15
ARP-1300 · Completed · progress not reported
$3,348.00 cumulative expenditures · $61,008.60 obligations · $100,000.00 adopted budget as of 2023-06-30
Latest Update
Public Health · Safe Public Facilities & Workplaces · Project 1.4.10 · Treasury evidence p. 2
ARP-1310 · Low alert · 83.3% dashboard progress
$244,925.28 cumulative expenditures · $979,701.13 obligations · $980,099.00 adopted budget as of 2023-06-30
Latest Update: Project is nearly complete, pending user acceptance of all microvwave links and systems. ✓Structural Reviews - 5/1/23 ✓Equipment Orders - 12/12/23 ✓Installation - 9/11/24
Public Health · Safe Public Facilities & Workplaces · Project 1.4.11 · Treasury evidence p. 11 p. 12
ARP-1320 · Low alert · progress not reported
$36,675.00 cumulative expenditures · $36,675.00 obligations · $9,325,000.00 adopted budget as of 2023-06-30
The Commissioners Court awarded the three bids of more than $6 million for this project. Contract development is underway. There is an additional $2 million underway as well for the Sobering/Diversion Center concept. An agreement with EHN is in the works. A previous RFP had no responses, so we are working on a direct agreement with EHN for these services.
Critical Infrastructure & Support Services · Critical Service Facilities · Project 2.4.1 · Treasury evidence p. 18
ARP-1330 · Low alert · 75% dashboard progress
$50,000.00 cumulative expenditures · $1,126,524.50 obligations · $4,000,000.00 adopted budget as of 2023-06-30
Latest Update - Phase 1 of the 2nd floor remodel continues as scheduled with visible progress of flooring, counters and built-ins now in place. Furniture vendor has tour and completed their final sizing/dimension planning in preparation of the furniture installation. As we prepare to move into the next phase of construction, space will become more limited, close coordination with other contractors on site will be essential to keep everything running smoothly and safely. Preliminary discussion continues regarding the future relocation of staff as 2nd floor space becomes available and anticipated space on the 1st floor transitions into future construction spaces.
Public Health · Safe Public Facilities & Workplaces · Project 1.4.12 · Treasury evidence p. 16
ARP-1340 · Completed · 100% dashboard progress
$858,398.16 cumulative expenditures · $931,298.16 obligations · $2,255,400.00 adopted budget as of 2023-06-30
Project completed pending final invoices
Critical Infrastructure & Support Services · Critical Service Facilities · Project 2.4.2 · Treasury evidence p. 5
ARP-1350 · Completed · 100% dashboard progress
$197,352.50 cumulative expenditures · $626,359.00 obligations · $626,359.00 adopted budget as of 2023-06-30
Latest Update ✓Project Complete - 3/3/25 ✓Construction Phase - 11/1/24
Critical Infrastructure & Support Services · Critical Service Facilities · Project 2.4.3 · Treasury evidence p. 11
ARP-1351 · Discontinued · progress not reported
$102,044.10 cumulative expenditures · $187,295.00 obligations · $187,295.00 adopted budget as of 2023-06-30
Latest Update
Critical Infrastructure & Support Services · Critical Service Facilities · Project 2.4.4 · Treasury evidence p. 13
ARP-1360 · Completed · 100% dashboard progress
$34,797.79 cumulative expenditures · $39,245.62 obligations · $85,000.00 adopted budget as of 2023-06-30
Latest Update All listed project items are now completed.
Public Health · Safe Public Facilities & Workplaces · Project 1.4.13 · Treasury evidence p. 12
ARP-1370 · Completed · progress not reported
$64,130.00 cumulative expenditures · $64,130.00 obligations · $64,130.00 adopted budget as of 2023-06-30
Latest Update This project was completed as part of ARP-1371.
Economic Recovery Efforts · External Agency Funding Assistance · Project 3.3.1 · Treasury evidence p. 16
ARP-1371 · On track · progress not reported
$1,874,599.10 cumulative expenditures · $9,083,780.13 obligations · $10,638,987.00 adopted budget as of 2023-06-30
Latest Update External agencies have begun submitting monthly reimbursement requests.
Economic Recovery Efforts · External Agency Funding Assistance · Project 3.3.2 · Treasury evidence p. 7 p. 8
ARP-1460 · Completed · progress not reported
$1,202,087.10 cumulative expenditures · $1,204,074.63 obligations · $2,486,269.00 adopted budget as of 2023-06-30
Latest Update
Administrative Operations · Revenue Replacement (Operating & Personnel) · Project 4.1.4 · Treasury evidence p. 32
ARP-1480 · Status pending · progress not reported
$0.00 cumulative expenditures · $0.00 obligations · $0.00 adopted budget as of 2023-06-30
The dashboard provides no narrative update for this project.
Administrative Operations · Revenue Replacement (Operating & Personnel) · Project 4.1.5 · Treasury evidence p. 27
ARP-1490 · On track · progress not reported
$0.00 cumulative expenditures · $0.00 obligations · $0.00 adopted budget as of 2023-06-30
Latest Update This project is ongoing. There will be an upcoming item for the Commissioner's Court to discuss continuing funding on June 5, 2023.
Administrative Operations · Professional Services & Technology · Project 4.2.3 · Treasury evidence p. 20
ARP-1500 · On track · progress not reported
Latest Update Partnership with The Ferguson Group is ongoing.
Administrative Operations · Professional Services & Technology · Project 4.2.4 · no row in the June 2023 report
ARP-1510 · Status pending · progress not reported
$0.00 cumulative expenditures · $0.00 obligations · $0.00 adopted budget as of 2023-06-30
The dashboard provides no narrative update for this project.
Administrative Operations · Revenue Replacement (Operating & Personnel) · Project 4.1.6 · Treasury evidence p. 21
ARP-1520 · Status pending · progress not reported
The dashboard provides no narrative update for this project.
Administrative Operations · Revenue Replacement (Operating & Personnel) · Project 4.1.7 · no row in the June 2023 report
ARP-1530 · On track · progress not reported
Latest Update Monitoring of this fund is ongoing.
Administrative Operations · Financial Reserves · Project 4.3.1 · no row in the June 2023 report
ARP-1540 · On track · progress not reported
$148,259.98 cumulative expenditures · $218,270.94 obligations · $420,000.00 adopted budget as of 2023-06-30
Latest Update This fund continues to be monitored by the administrative team.
Public Health · Safe Public Facilities & Workplaces · Project 1.4.14 · Treasury evidence p. 17
ARP-1560 · On track · progress not reported
Latest Update Monitoring of this fund is ongoing.
Administrative Operations · Financial Reserves · Project 4.3.2 · no row in the June 2023 report
ARP-4000 · Discontinued · progress not reported
$59,985.00 cumulative expenditures · $59,985.00 obligations · $100,000.00 adopted budget as of 2023-06-30
No activity. this project is no longer being pursued.
Public Health · COVID-19 Testing & Vaccination · Project 1.3.5 · Treasury evidence p. 25
ARP-4010 · Discontinued · progress not reported
Latest Update This project is being discontinued due to a lack of recipients. Community Services noted that a similar project is offered by FEMA and thus may be duplicative and contributing to low enrollment. Funds are being evaluated for reprogramming.
Critical Infrastructure & Support Services · Community Assistance & Support Services · Project 2.3.4 · no row in the June 2023 report
ARP-4020 · Completed · progress not reported
$141,700.00 cumulative expenditures · $141,700.00 obligations · $675,000.00 adopted budget as of 2023-06-30
Latest Update
Critical Infrastructure & Support Services · Community Assistance & Support Services · Project 2.3.5 · Treasury evidence p. 3
ARP-4030 · High alert · progress not reported
$0.00 cumulative expenditures · $3,951,349.77 obligations · $3,951,349.77 adopted budget as of 2023-06-30
Phase 4 of the Sewer Project was completed and inspected last week. Contractor is preparing to start phase 9 and 10 on January 3rd. While the contractor preps this week, S.O. will be relocating the inmates out of these sections. Relocation expected to be completed by the end of the week. Latest Update
Critical Infrastructure & Support Services · Critical Service Facilities · Project 2.4.5 · Treasury evidence p. 6
ARP-4040 · High alert · progress not reported
$0.00 cumulative expenditures · $3,025,728.00 obligations · $3,025,728.00 adopted budget as of 2023-06-30
Pending update from project manager
Critical Infrastructure & Support Services · Critical Service Facilities · Project 2.4.6 · Treasury evidence p. 7
ARP-4050 · Completed · progress not reported
$158,500.00 cumulative expenditures · $158,500.00 obligations · $158,500.00 adopted budget as of 2023-06-30
Latest Update
Economic Recovery Efforts · External Agency Funding Assistance · Project 3.3.3 · Treasury evidence p. 4
ARP-4060 · Completed · progress not reported
Latest Update: Project is complete.
Public Health · General Public Health · Project 1.2.6 · no row in the June 2023 report
ARP-4070 · Completed · progress not reported
Latest Update
Critical Infrastructure & Support Services · Community Assistance & Support Services · Project 2.3.6 · no row in the June 2023 report
ARP-4080 · Completed · progress not reported
Latest Update
Critical Infrastructure & Support Services · Community Assistance & Support Services · Project 2.3.7 · no row in the June 2023 report
ARP-4090 · Status pending · progress not reported
The dashboard provides no narrative update for this project.
Administrative Operations · Revenue Replacement (Operating & Personnel) · Project 4.1.8 · no row in the June 2023 report
ARP-5010 · Status pending · progress not reported
The dashboard provides no narrative update for this project.
Administrative Operations · Revenue Replacement (Operating & Personnel) · Project 4.1.9 · no row in the June 2023 report
ARP-5020 · Completed · progress not reported
Latest Update
Public Health · Safe Public Facilities & Workplaces · Project 1.4.15 · no row in the June 2023 report
ARP-5030 · Status pending · progress not reported
The dashboard provides no narrative update for this project.
Administrative Operations · Revenue Replacement (Operating & Personnel) · Project 4.1.10 · no row in the June 2023 report
ARP-5040 · Status pending · progress not reported
The dashboard provides no narrative update for this project.
Administrative Operations · Revenue Replacement (Operating & Personnel) · Project 4.1.11 · no row in the June 2023 report
This is the newest project-level Treasury report currently posted on the County reports page, but it is a historical snapshot through June 30, 2023. It does not identify individual vendors, invoices or checks, and current dashboard status must not be treated as contemporaneous with these amounts. Tax Watch does not connect these totals to individual check-register rows without a shared transaction identifier.